Your bid price is not the only number that decides what you are paid on an Alberta Transportation and Economic Corridors tender. Three special provisions can add money to a progress payment, take money off it, or pay you for material before it goes in the ground. One of them is written so that you can lose by staying silent.
All of the documents below are issued by Alberta Transportation and Economic Corridors and marked “Classification: Public”. I read the library copies. In several of them the key numbers are blank placeholders, so none of this gives you a dollar figure.
Asphalt cement cost adjustment
The special provision (SPC_002) is a short insert. It says the Contract includes an asphalt cement cost adjustment under Specification 1.2.59 and states the Base Price Index for Asphalt Cement for that contract. In the library copy that value is “####”. The rules themselves are in Specification 1.2.59 (AMC_C294).
- The index is the BCRB Asphalt Index, using its Edmonton price.
- The base price is normally set before the tender is advertised.
- Each month’s index runs from the 26th of the previous month to the 25th of the current month, to match progress payment timing.
- If the monthly index sits between 0.95 and 1.05 of the base, inclusive, there is no adjustment that month. Below 0.95 the department gets a credit. Above 1.05 you get additional payment.
- Adjustments are separate lump sum items on the progress payment. Decreases are deducted and increases are added.
It covers only performance and penetration grade asphalt cements in asphalt concrete pavements. Hot-in-place recycling, liquid asphalt, emulsified asphalt and other products are out, and so are lump sum bid items. The calculation works from tonnes of acceptable mix and the percentage of new asphalt cement. Where the mix has reclaimed asphalt pavement, the new percentage is the actual asphalt cement percentage minus the RAP contribution from the accepted mix design.
Two things to settle before you sign. You may opt out by stating so in writing before the Contract is executed, and the choice covers the entire Work. Silence counts as participation. No opt-in or opt-out is allowed after execution. And the adjustment stops at the Construction Completion date: work completed after the specified or adjusted date is paid with no adjustment.
The designer notes say the clause is meant for tenders that span two construction seasons. Their example is a tender of December 8, 2020 with completion October 15, 2021, marked “1 construction season - No”.
Tariff Relief Events
SPC_014 is marked for inclusion in all highway and bridge tenders. It works in both directions.
What pays. A Tariff Relief Event needs Canada to legally enact Retaliatory Tariffs on or after seven days before the Closing Date and Time. Retaliatory Tariffs are tariffs enacted by the Government of Canada on Tariff Goods imported from the United States, in direct response to US tariffs on Canadian goods. When one occurs, the department pays the increased costs. Inflation, currency exchange rates, general supply chain cost escalation, markups, administrative charges on tariffs and interest carrying costs are not compensable.
What you have to do.
- Give no less than 14 days' written notice after Canada enacts a tariff.
- Give no less than 7 days' written notice of your purchase or mitigation intention, and consult the department.
- Within 7 days after contract execution, list the Tariff Goods you expect to buy with unit cost and quantity, the Retaliatory Tariffs known seven days before closing, and the anticipated cost of those tariffs built into your tender.
- Supply evidence within 30 days after being impacted: invoices, receipts, tariff notices, import documents and proof of payment of subcontractors and suppliers. It must be acceptable to the department “in the exercise of its sole and unfettered discretion”.
- Each fiscal year, report amounts actually paid.
Payment depends on you having applied to every other level of government with a reimbursement program, and on confirmation that none has paid the cost. The department may ask for a statutory declaration at any time. Your payment request can contain only the tariff claim and no other claim under the Contract. Accepted costs are paid within 28 days after the related portion of the Work is completed and invoiced. Wastage on Tariff Goods over 5%, item by item, is not considered.
What claws back. Tariffs in effect eight days before closing belong in your bid price. If they are rescinded or reduced on or after seven days before closing, you reimburse the department for the actual savings.
The Tariff Goods list in the library copy includes metal and lumber in signs and guardrail, metal in culverts, street lights, traffic signals, line marking paint, bridge deck joints, bridge bearings, and metal in bridge girders, piling and bridge rail. Equipment and tools are excluded. So are temporary works materials, to the extent the Consultant considers them capable of re-use on other work.
Interim Payment for Supply of Materials
SPC_015 is for all highway and combined highway and bridge tenders, not bridge-only tenders. Bridge materials are excluded because the bridge standard specifications have their own interim payment clauses.
You “may request” interim payment, but only for the materials listed in the special provision. The library copy shows that list as blank placeholders. The payment is the lesser of actual supplier invoices or 75% of the applicable bid item that incorporates the materials.
The conditions sit in the General Specifications, Edition 16, clause 1.12 (AMC_C218):
- A written request from you.
- The materials inventoried for more than 30 days before incorporation.
- Supply, fabrication, inspection and testing complete.
- No separate payment in the applicable specification.
- Written consent of Surety or an Irrevocable Letter of Credit for the total interim payment.
Payments are monthly and are not acceptance of the materials. The interim payment is deducted when the bid item is paid, or when all work under that item is complete.
Read the percentage twice. Edition 16 clause 1.12.2 states the limit as “50% of the applicable bid item”. SPC_015 states 75%. The documents do not say why. SPC_015 says “Further to AMC_218”, and the library copy of AMC_C218 is Edition 16 from 2019. Whether a later version exists is not stated.
How diesel compares
The Diesel Fuel Cost Adjustment (SPC_001, with AMC_C280) has the same shape as the asphalt one. It points to Specification 1.2.58 and states a Base Price Index for diesel, shown as “####” in the library copy.
| Asphalt cement | Diesel | |
|---|---|---|
| Specification | 1.2.59 (AMC_C294) | 1.2.58 (AMC_C280) |
| No adjustment between | 0.95 and 1.05 | 0.90 and 1.10 |
| Index | BCRB Asphalt Index, Edmonton price | Average of Edmonton and Calgary monthly average retail diesel prices, Statistics Canada Table 18-10-0001-01 |
| Lump sum items | Excluded | Excluded |
| Opt out | Written, before execution, entire Work | Written, before execution, entire Work |
Diesel applies only above size thresholds, including grading over 150 000 cubic metres, asphalt concrete pavement over 20 000 tonnes, and granular base course over 20 000 tonnes. It is paid on fixed consumption rates, not your actual fuel use: 2.4 litres per tonne for asphalt concrete pavement, 1.6 litres per m3 for grading, and 0.035 litres per tonne-km for haul. The document says no allowance is made for your choice of equipment, type of fuel, methods, efficiencies or haul distances.
What the documents do not say
- They do not say what changed from any earlier version. SPC_014 and SPC_015 carry no revision notes.
- They do not say which tenders will include the asphalt, diesel or tariff provisions. The only guidance is in the designer notes.
- The base index values are blank, so no dollar figures are available.
- They do not say whether Retaliatory Tariffs currently apply to any Tariff Goods.
- The Tariff Goods list is a template that Consultants customize per tender, so a given tender’s list may differ.
- They do not say whether the asphalt, tariff and diesel mechanisms can all be claimed on one contract.
- I did not check the library copies against the issuer’s live pages.
The library lists SPC_002 (October 13, 2023), AMC_C294 (September 26, 2023), SPC_014 (August 8, 2025), SPC_015 (April 9, 2026) and SPC_001 (September 26, 2023) as current.
Checked against Alberta Transportation and Economic Corridors SPC_002, AMC_C294, SPC_014, SPC_015, SPC_001 and AMC_C280, and General Specifications Edition 16, on October 27, 2026.