Working near a pipeline in Alberta: the lead times before you dig

Pipeline companies get days, and sometimes weeks, to answer consent and approval requests. Here are the CER and Alberta waiting periods, and what the documents leave unsaid.

If your trench is near a pipeline, some of the waiting is not yours to control. The pipeline company gets 10 working days to answer a consent request under the federal rules, and Alberta’s Pipeline Rules give a licensee 21 days to answer an approval request in writing. Put those numbers in the schedule before you price the job, not after you mobilize.

Two sets of rules are in play. The Canada Energy Regulator (CER) covers federally regulated lines. The Alberta Energy Regulator (AER) covers lines under Alberta’s Pipeline Act and Pipeline Rules. The documents I checked do not tell you which regulator covers a given line, so that is a question for the locate.

The CER’s 30 metres

The Pipeline Damage Prevention Regulations, Authorizations (SOR/2016-124) define the prescribed area as a strip of land 30 m on each side of the pipe centreline. The CER’s Construction Near Pipelines guide (2022) says that area applies whether or not there is a right-of-way, and that the right-of-way is usually smaller. So the pipeline can matter to you well outside the fenced or signed strip.

Inside that area, a ground disturbance is authorized only if you have the pipeline company’s written consent and have made a locate request. Three more points from the Authorizations regulations:

  • The work must be finished within two years of getting consent, unless the consent sets a different period.
  • If the pipeline company suspends its consent, the authorization is suspended and the work must stop for as long as the suspension lasts.
  • You must tell the pipeline company immediately about any contact with a pipe or its coating.

The CER guide also says you must contact the One-Call Centre for work that disturbs the ground 30 cm or deeper near a federally regulated facility. It says parking vehicles on the right-of-way needs written consent. It also says each day a violation continues counts as a separate violation, with no maximum total fine.

The CER’s waiting periods

You make the locate request at least three working days before the work starts. It goes to a one-call centre if one exists in the area, and otherwise straight to the pipeline company. The three-day period does not apply in an emergency, where the request goes in as soon as possible before work starts.

The pipeline company’s clocks are in the Obligations of Pipeline Companies regulations (SOR/2016-133):

  • Consent: 10 working days to say whether consent is granted or refused, with reasons if refused.
  • Application information: 10 working days to give you what you need to apply to the Regulator for authorization.
  • Locate: three working days, or a longer period agreed with you, to give written safety practices and mark its pipes. Markings go at intervals of no more than 10 m along each pipe.

A working day is any day that is not a Saturday, a Sunday or another holiday.

Alberta’s Pipeline Act and Pipeline Rules

Section 42 of the Pipeline Act bars ground disturbance in a pipeline right of way without the licensee’s approval. Section 32(1) requires you to tell the licensee the nature of the disturbance and the proposed schedule. If a ground disturbance contacts a pipeline, it must stop immediately, you must advise the licensee, and it cannot restart without the licensee’s approval.

The Pipeline Rules (AR 125/2023) set the distances:

  • Section 45(1): a search distance of 30 metres from the perimeter of the dig area.
  • Section 43(2): approval is required for ground disturbance within 5 metres of the centreline where there is no right of way.
  • Section 51(1): once work approaches within 5 metres of a pipeline, you expose it by hand until it is positively identified and its orientation is known, before any further mechanical excavation.
  • Section 51(1) also requires a licensee representative, or a delegate the licensee accepts, to be present when the pipeline is exposed.

Section 42 of the Rules bars a licensee from charging fees for locating, marking, consents, supervision or inspections.

The AER brochure Safe Excavation Near Pipelines (2024) says the same 30 m beyond the dig area. It says the right-of-way is usually less than the 30 m controlled area, but may sometimes be more. It says no machinery may dig within 60 cm of the pipeline unless a pipeline owner representative is present. It also warns that not every underground service is registered with Utility Safety Partners (formerly Alberta One-Call), and that you should not assume it is.

Alberta’s waiting periods

Under section 45(2) of the Pipeline Rules, for work in a controlled area or right of way you notify Utility Safety Partners at least 3 days and not more than 10 days before starting, excluding Saturdays, Sundays and holidays. The licensee must then locate and mark no later than 3 days after being notified, again excluding Saturdays, Sundays and holidays. That can be longer where locator availability or an agreement requires it.

A licensee must answer an approval request in writing within 21 days of the request. If the licensee cannot respond, the request goes to the Regulator.

The numbers side by side

ItemSourcePeriod
Your locate request before work startsCER Authorizations regulationsAt least three working days
Pipeline company answers a consent requestCER Obligations regulations10 working days
Pipeline company supplies application informationCER Obligations regulations10 working days
Pipeline company marks and sends safety practicesCER Obligations regulationsThree working days, or longer if agreed
Notice to Utility Safety PartnersPipeline Rules s.45(2)At least 3 days, not more than 10 days, excluding Saturdays, Sundays and holidays
Licensee locates and marksPipeline RulesNo later than 3 days after notice, excluding Saturdays, Sundays and holidays, unless a longer period is needed
Licensee answers an approval requestPipeline Rules21 days

What the documents do not say

  • The AER brochure says “at least two full working days” before digging in the controlled area. Pipeline Rules s.45(2) says at least 3 days, excluding Saturdays, Sundays and holidays. The documents do not reconcile the two, and I will not say which governs.
  • The CER’s three working days and Alberta’s three days belong to different regulators and different pipelines.
  • Section 45(2) caps the notice at 10 days before starting. What happens to a request older than that is not stated.
  • The 21-day approval period is not stated to be linked to the Utility Safety Partners notice window, so I have not added them into one total.
  • No document says how many calendar days a schedule should carry.
  • None of the documents give penalty amounts for Alberta or dollar amounts for the CER.
  • None of the sources, as extracted, say what changed between editions, so I make no claim about that.

Checked against the CER Pipeline Damage Prevention Regulations (Authorizations, SOR/2016-124, and Obligations of Pipeline Companies, SOR/2016-133), the CER guide Construction Near Pipelines (2022), Alberta’s Pipeline Act, the Pipeline Rules (AR 125/2023) and the AER brochure Safe Excavation Near Pipelines (2024) on October 27, 2026.