If you bid county bridge and culvert work, the bridges the Province approved for funding this year are on a list it published on July 22, 2026. Every line carries a bridge file number, and on the last two years' pattern those bridge files show up as tenders on Alberta Purchasing Connection about nine months after the list comes out.
What the list is
The Local Road Bridge Program is one stream of Alberta Transportation and Economic Corridors' Strategic Transportation Infrastructure Program (STIP). It funds municipalities for local bridge projects, including engineering, maintenance, rehabilitation and replacement. The Province pays 75% of eligible costs and the municipality 25%, and the program page says “private sector contractors and suppliers must be used to carry out all work.” Applications are rated provincewide on criteria that include need, safety, the current condition of the structure and truck traffic.
Municipalities have to apply by November 30 to receive funding the following year. The approved projects then come out as a list. The last three were dated June 27, 2024, July 21, 2025 and July 22, 2026, and all of them are on the Province’s STIP approved projects page.
The provincial share approved:
- 2024 list: 72 projects, $47.3 million
- 2025 list: 38 projects, $23.8 million
- 2026 list: 28 projects, $19.0 million
Every approved project carries the bridge file number of the structure. That number is what makes the list useful: it is the number the matching below found in the tender titles.
How long from the list to the tender
I matched the bridge file numbers on the 2024 to 2026 lists against tenders posted on Alberta Purchasing Connection, searched on October 28, 2026. Of 138 local road bridge approvals, 70 matched a tender by bridge file number and owner.
- For the 2024 and 2025 lists, the median time from the date of the list to the tender posting was 264 days, about nine months. The middle half fell between 160 and 322 days.
- 35 of those 63 tenders were posted between January and June of the year after the list.
- Across all 70 matched tenders, 35 were posted in March, April or May.
- 11 of the 70 were posted before the list carrying their bridge file was published.
The matching has limits. The lists do not give a tender date for each bridge. A bridge file that did not match may have been posted on another portal, combined with other bridge files under one title, or not tendered yet.
The 2026 list, bridge by bridge
The 2026 list has 28 local road bridge projects with a provincial share of $18,985,694.60. Twenty-one are culvert replacements, six are bridge replacements and one is a bridge rehabilitation. By October 28, 2026, 7 of the 28 matched a tender on Alberta Purchasing Connection. The other 21 had no match.
| Owner | Bridge file | Work | Provincial grant | On APC by October 28, 2026 |
|---|---|---|---|---|
| Athabasca County | 07835 | Culvert Replacement | $375,000.00 | No match found |
| Athabasca County | 70771 | Culvert Replacement | $731,250.00 | No match found |
| Athabasca County | 73786 | Culvert Replacement | $787,500.00 | No match found |
| Brazeau County | 75463 | Culvert Replacement | $861,000.00 | No match found |
| Buffalo Lake Metis Settlement | 85461 | Culvert Replacement | $834,000.00 | No match found |
| Cardston County | 1922 | Culvert Replacement | $350,627.25 | No match found |
| Clearwater County | 78350 | Culvert Replacement | $2,062,500.00 | No match found |
| County of Grande Prairie No. 1 | 73329 | Bridge Rehabilitation | $201,750.00 | Posted January 19, 2026 |
| County of Minburn No. 27 | 72570 | Bridge Replacement | $367,500.00 | Posted April 10, 2026 |
| County of Newell | 71858 | Culvert Replacement | $827,681.25 | No match found |
| County of Newell | 77577 | Culvert Replacement | $887,740.50 | No match found |
| County of Wetaskiwin No. 10 | 2485 | Bridge Replacement | $611,250.00 | No match found |
| Cypress County | 72441 | Culvert Replacement | $325,500.00 | No match found |
| Cypress County | 73577 | Culvert Replacement | $279,750.00 | No match found |
| Municipal District of Bonnyville No. 87 | 76626 | Culvert Replacement | $1,425,000.00 | Posted April 8, 2026 |
| Municipal District of Peace No. 135 | 75201 | Culvert Replacement | $900,000.00 | No match found |
| Municipal District of Pincher Creek No. 9 | 76203 | Culvert Replacement | $366,838.10 | No match found |
| Municipal District of Taber | 84383 | Culvert Replacement | $256,305.00 | No match found |
| Northern Sunrise County | 81341 | Culvert Replacement | $780,000.00 | No match found |
| Parkland County | 13218 | Bridge Replacement | $450,000.00 | Posted August 13, 2026 |
| Parkland County | 85064 | Bridge Replacement | $112,500.00 | Posted August 31, 2026 |
| Red Deer County | 06865 | Culvert Replacement | $431,527.50 | No match found |
| Saddle Hills County | 72957 | Culvert Replacement | $1,390,500.00 | No match found |
| Smoky Lake County | 06872 | Bridge Replacement | $759,000.00 | No match found |
| Smoky Lake County | 76438 | Culvert Replacement | $399,000.00 | No match found |
| Town of Crossfield | 75095 | Culvert Replacement | $328,725.00 | Posted September 8, 2025 |
| Westlock County | 13192 | Culvert Replacement | $375,000.00 | No match found |
| Wheatland County | 76863 | Bridge Replacement | $1,508,250.00 | Posted January 22, 2026 |
The grant is the provincial share only, not the full project cost. A posting date before July 22, 2026 is one of the tenders that came out before the list was published.
What to do with it
Find the counties and MDs you work in on the table, and keep the bridge file numbers beside your tender alerts. On the pattern of the last two lists, you would expect most of the 21 unmatched bridge files to be tendered next spring, with March to May the busiest months. When a title on Alberta Purchasing Connection carries one of those bridge file numbers, you already know the Province has put money behind it.
The applications that decide the next list are due November 30. If the last three lists are a guide, that list comes out in late June or July.
Why there is so much of this work, and how far behind the renewal money is, is the subject of a follow-up post in December.
Checked against the STIP 2024, 2025 and 2026 approved project lists and Alberta Purchasing Connection postings on October 28, 2026.