Schwehr Projects · Blog · 10 of 15

Exclusionary periods for winter work on Alberta highway contracts

Alberta Transportation and Economic Corridors has a one-page amendment to Spec 1.2 on winter work. It states no dates, so check the tender's special provisions before you set stop and restart dates.

If you are pricing a roadway job that can run through the winter, do not assume the November 1 to April 30 stop you read in the 2019 General Specifications still applies. Alberta Transportation and Economic Corridors has an amendment that deletes the clause behind it. The amendment gives no replacement dates, so your stop and restart dates have to come from the tender itself.

What the amendment is

Alberta Transportation and Economic Corridors issues a one-page amendment titled “1.2, General, Re: Exclusionary Periods Non Bridge Winter Work”. The library lists it as published August 14, 2023, with status current. It is marked for roadway projects where work can be carried out through winter months, and for use when the 2019 General Specification is referenced.

It does two things. Amendment 5.1 deletes Subsection 1.2.39.3 of Spec 1.2. Amendment 5.2 deletes clause (i)(b) of Subsection 1.2.40, “Failure to Complete on Time”.

What those two clauses said

In the General Specifications (Edition 16, January 2019), Subsection 1.2.39.3 applies to roadway contracts and combined roadway-and-bridge contracts. When an adjustment grants a new completion date on or after November 1, the Department excludes the period from November 1 to April 30, provided a seasonal shutdown is granted. The worked example in the book: a completion date of October 15 and a 20-calendar-day extension give an adjusted completion date of May 4 of the following year. If the adjusted date falls on or after November 1, bad weather between November 1 and April 30 is not a reason for delay, and no further extensions are granted for that period.

Clause (i)(b) of Subsection 1.2.40 is the other one. For all contracts other than bridge-only or seal coat contracts, no Damages for Delay are assessed from December 1 to April 30 of the following year. The amendment deletes it.

Damages for Delay under Spec 1.2.40 are a stipulated $3,000.00 per calendar day, reduced to $500.00 per calendar day if all Work is complete except minor cleanup.

What the documents do not say

The amendment only deletes. It states no replacement dates, and it does not say what exclusion applies to a roadway contract worked through winter. Any such dates would sit in the individual tender’s special provisions.

Other gaps:

  • The documents do not say what changed between the 2019 text and the 2023 amendment page, and the library has no change summary for Spec 1.2.
  • The page is dated “November 2019” at its foot, while the library’s August 14, 2023 date comes from the HTTP Last-Modified header. The documents do not say when it was first issued.
  • The documents do not say which tenders use the amendment, or how a bidder is told it applies.
  • The documents do not say how winter work or standby is priced, beyond the statement that shutdown plan costs are not separately paid.

It is one page and worth reading before your next tender.

Seasonal shutdown under Spec 1.2.43

A shutdown is a separate matter from the exclusion. Under Spec 1.2.43, a roadway or combined contractor may request a seasonal or prolonged shutdown on or after November 1, or when work cannot or should not progress because of prolonged inclement weather, specification requirements, safety or environmental reasons. It takes a joint meeting and a Contractor-developed shutdown plan, and the Contractor “may only shutdown if the shutdown is agreed to by the Department”. Spec 7.1.10 of the Standard Specifications for Highway Construction (Edition 16, 2019) requires you to give proposed shutdown dates with the request.

Three points for the price:

  • No Damages for Delay are assessed during a shutdown the Department has agreed to, as long as you comply with Spec 1.2.43.
  • You carry the shutdown costs. The Department makes no separate or additional payment for them.
  • Until the Shutdown Notification is issued, snow removal and ice control are your responsibility.

Inclement weather after the specified or adjusted completion date is not a reason for delay, and no Damages for Delay are assessed for calendar days lost to it after that date.

Bridge-only and seal coat contracts

Bridge-only contracts are generally not eligible for the November 1 exclusionary period. You keep working on bridge projects after November 1 unless the Consultant and the Department judge that the work cannot or should not progress.

Seal coat contracts have their own exclusions:

Seal coat typeExcluded period
Chip sealSeptember 16 to April 30
Micro-surfacing, graded aggregate seal coat, double seal coat, slurry sealSeptember 30 to April 30

The Standard Specifications also limit slurry seal placement to May 1 to September 15, and micro-surfacing to June 1 to September 15.

Cement stabilized base course cut-off dates

Alberta Transportation and Economic Corridors publishes a special provision, “Construction Cut-off Dates for Cement Stabilized Base Course and Asphalt Stabilized Base Course”, dated August 21, 2024, status current. It adds to Section 3.9.4.1 of Spec 3.9, which stays in effect. The cut-off is a blank, to be filled in per project, so the document prints no calendar date and gives no standard cut-off for CSBC or ASBC. Read the tender for it.

What it requires:

  • If the CSBC is not finished by the cut-off, the project must be left in a safe condition. The CSBC lift must end at the same location across the full roadway width, with an adequate ramp for traffic.
  • All CSBC placed during the season must be covered with Asphalt Stabilized Base Course before seasonal shutdown.
  • It supersedes Section 3.9.4.12 and sets the gap between finishing and compacting the CSBC and placing the ASBC at no less than ten days and no more than twenty days. The standard Spec 3.9.4.12 sets only a minimum of ten days and allows asphalt stabilized base course or asphalt concrete pavement as the cover.

Spec 3.9 also bars mixing or placing CSBC at or below 5ºC, or when the temperature may fall below 5ºC within 24 hours, unless adequate protection is used. It bars placing CSBC on frozen subgrade. Frost-damaged CSBC is replaced at your expense. Completed CSBC cures for a minimum of five days before opening to normal traffic, and the Consultant may extend that if the temperature drops below 5ºC during those days.

For asphalt concrete, the Standard Specifications require you to schedule so that, before winter shutdown, all S3 mix material is covered by the next lift or fog coated.

Where to read it

The documents are the 2019 General Specifications (Edition 16, January 2019), the Standard Specifications for Highway Construction (Edition 16, 2019), the Spec 1.2 exclusionary periods amendment, and the CSBC and ASBC cut-off special provision, all from Alberta Transportation and Economic Corridors. The landing pages on the issuers' domains were not checked, so currency beyond the library’s “current” status is unconfirmed.

Checked against the Alberta Transportation and Economic Corridors General Specifications (Edition 16, 2019), Standard Specifications for Highway Construction (Edition 16, 2019), Spec 1.2 exclusionary periods amendment and the cement and asphalt stabilized base course cut-off special provision on October 27, 2026.