Commissioning an EPCOR water main: the waiting time to price in

EPCOR's flushing, testing and disinfection rules put notice periods and hold times between laying the pipe and putting it in service. Here is what the documents state, and what they leave out.

If you are pricing a water main that EPCOR Water Services will take over in Edmonton, the pipe in the ground is only part of the schedule. Between the last joint and the main going into service sit written notices, hold times and a sampling window, and every one of them is a number you can find in EPCOR’s documents.

The documents do not use the term “standby days”. What they give you is the list of waiting periods. How many days to carry in a bid is your call, and the documents do not make it for you.

The sequence EPCOR requires

EPCOR Water Services issued its Water Flushing and Testing Guidelines in February 2024 (dated February 27, 2024). The library lists them as current and adopted by Edmonton. The guidelines say they detail the requirements for flushing, hydrostatic and disinfection plans, submitted with the project’s overall plan.

The order is flushing, then hydrostatic testing, then disinfection and sampling. The only way around that order is a variance approved by the EWS Engineer before commissioning.

Every commissioning plan goes to EWS for review before any commissioning activity. Activity EWS has not accepted is at the Developer’s own risk and may be subject to additional testing. Plan for the possibility of retesting.

A stamped and sealed copy of the approved plans must be on site during all flushing and testing. Every activity is recorded on the forms on EPCOR’s website.

Flushing

Each flushing run must be under 450 m, with 200 m as the ideal length. The flushing spreadsheet sets the required discharge volume at five times the pipe volume of the run.

The flushing report, which is one of EPCOR’s four forms, records for each section:

  • the purpose, date, and start and end times
  • pipe diameter in mm and length in m
  • flow rate in L/s and estimated volume in L
  • the dechlorination method

Alberta’s Standards and Guidelines for Municipal Waterworks, Part 1 Waterworks (2012, revised 2021), requires dechlorination before chlorinated main water is discharged to the environment. It says that water shall not be drained directly into the storm sewer or an open body of water.

Hydrostatic testing

The Water Flushing and Testing Guidelines limit a test run to under 450 m for mains 400 mm and smaller, and under 800 m for mains 450 mm and larger. Each segment may contain only one pipe material.

EPCOR Water Services' DCS Volume 4: Water, edition December 2024, is current and adopted by Edmonton. It sets its own section limits: 450 m for mains 100 mm to 300 mm, and 800 m for mains 350 mm or larger. It also treats fused PVC and jointed PVC as different materials for testing. Check which limit your main falls under before you lay out the test sections, because the two documents split the diameters at different points.

Volume 4 gives these test conditions:

  • For PVC, the test pressure is the highest of 125% of working pressure at the highest point, 150% of working pressure at the lowest elevation, or 1034 kPa (150 psi). The minimum duration is 2 hours.
  • Steel water pipe is tested for not less than 4 hours. Cement-mortar-lined steel is filled 24 hours beforehand.
  • Pressure must be held within ± 20 kPa of the specified pressure. The main is re-pumped to test pressure after the first 30 minutes.
  • No allowance can be made for services, appurtenances or in-line valves.
  • The test gauge must be calibrated and certified annually, and the certification goes in with all test results.

Inspectors must be told the date, time and location of a hydrostatic test at least 24 hours before it. Volume 4 says that failing to notify “may result in the tests being rejected, requiring new tests to be completed.” The written result goes to the EPCOR Water Inspector within 24 hours. A failed test also needs immediate verbal notice.

Thrust blocks and other restraining devices must be in place and properly cured according to Section 13 before the test.

Disinfection and sampling

Part 1 says new mains are disinfected and flushed in accordance with AWWA C651. Volume 4 says its disinfection criterion uses AWWA C651 as well. The specific doses and hold times in this section are EPCOR’s, from Volume 4.

For continuous-feed chlorination:

  • Written notice to the EPCOR Water Inspector is required 72 hours before starting.
  • The feed must keep the water between 25 mg/L and 50 mg/L free chlorine.
  • Chlorinated water stays in the main no less than 24 hours.
  • After that, a residual under 10 mg/L means flush and re-chlorinate.
  • Written results with the time of test go to the Inspector within 4 hours of completing the test.

For granular chlorination, contact time is at least 24 hours above 5°C and 48 hours at or below 5°C. The pass residual is more than 0.2 mg/L.

Chlorine injection must be within 3.0 m of the disinfection section’s boundary valve where possible. Hydrants are not permitted for chemical feed.

Samples for chlorine, bacteriological and taste and odour (T&O) testing are collected at 400 m intervals, at the end of the main, and at the end of each branch longer than 1 pipe length. Volume 4 says bacteriological samples are not taken from fire hydrants, and they must reach the lab within 6 hours of collection.

Existing mains that were depressurized during construction must be disinfected to the same standard as new mains.

The waiting periods in one place

StepWhat the documents state
Hydrostatic testInspector told date, time and location at least 24 h before
Continuous-feed chlorinationWritten notice 72 h before starting
Chlorine contact, continuous feedNo less than 24 hours
Chlorine contact, granular24 hours above 5°C, 48 hours at or below 5°C
Bacteriological samplesNo less than 16 h and no more than 7 days after the chlorine test passes
Two bacteriological setsCollected 16 hours apart, no flushing before or between
T&O sampling noticeWritten notice at least 72 h beforehand
Flushing to T&O samplingMinimum hold of 16 hours

Two consecutive passing bacteriological samples are required at each sampling point before T&O sampling. If passing T&O samples are not achieved within 14 days of the last passing bacteriological samples, a single set of refresher bacteriological samples is required. If any refresher sample fails, two successive passing results are required to put the main into service.

Winter commissioning

The guidelines define winter commissioning as system water temperature at or below 5 degrees Celsius. It has been permitted since the 2023 construction season. The guidelines also say it is subject to short notice cancellation due to weather limitations, at the EWS Inspector’s discretion. The longer 48-hour granular contact time applies at that temperature too.

A change in chlorination method is classed as major and needs EWS acceptance. A change in hydrostatic run length is minor up to 450 m for distribution mains and 800 m for transmission mains.

Reports, and when they are due

EPCOR has four report forms: the Hydrostatic Testing Report, the Chlorine Residual and Bacteriological Sampling Report, the Thrust Block Report and Concrete Test Results, and the Flushing Report. The first two have a space for the engineer’s or professional technologist’s seal.

The hydrostatic form certifies the tests were done to Edmonton’s Design and Construction Standards and AWWA C200, with gauges calibrated beforehand. The bacteriological form certifies the Edmonton standards, the Province of Alberta Guidelines for Municipal Waterworks, and AWWA C651-14. The thrust block form records, for each concrete batch, the ticket number, placement date and time, ambient temperature, batch volume and cumulative volumes.

Volume 4 Table 1.1 sets the submission deadlines:

  • Coupon test results, fused PVC test reports, pull data for directional drilling, weld reports and X-ray records: 2 weeks prior to hydrostatic testing.
  • Flushing report, hydrostatic test results, pressure gauge calibration results and taste and odour results: prior to C.C.C. inspection.
  • Thrust block report and concrete test results: prior to C.C.C. signing by Engineer.

Volume 4 requires a concrete thrust block at each dead end, valve, tee, bend, hydrant, reducer and fitting, and at any change in pipe diameter or direction. Where the geotechnical report shows soil bearing capacity under 72 kPa, the specific detail on the drawings applies.

What the documents do not say

  • They do not give a number of standby days to carry.
  • They do not give lab turnaround time, EPCOR inspector response times, or the cost of a failed test or retest.
  • Part 1, in the pages read, gives no hydrostatic test pressure or duration and no thrust block requirement. Those figures come from Volume 4.
  • Part 1 refers to AWWA C651 but was not found to state a 25 mg/L dose or a hold time. Those numbers are EPCOR’s.
  • Test pressure for pipe materials other than PVC and steel, such as HDPE or ductile iron, was not read.
  • The library copy of Part 1 is a mirror hosted by the City of Calgary. Whether it matches the Alberta Environment and Parks original was not checked.
  • Nothing here compares this edition of Volume 4 with an earlier one, so no change is claimed.

Checked against the EPCOR Water Flushing and Testing Guidelines (February 2024), EPCOR DCS Volume 4: Water (December 2024), EPCOR’s four commissioning report forms, and Alberta’s Standards and Guidelines for Municipal Waterworks, Part 1 (2012, rev. 2021), on October 27, 2026.