Edmonton Complete Streets Version 6: what to check before you price

Version 6 design standards and details are dated November 2025. I could not find the matching construction specifications, and an alley amendment from May 8, 2026 replaces two drawings.

If you are pricing City of Edmonton street or alley work, find out which edition of the Complete Streets book the tender points to before you open the drawings. Version 6 of the design standards and standard details is dated November 2025, but the construction specifications that go with it are a separate question, and a price built on the wrong edition is a price built on the wrong book.

Which projects Version 6 applies to

The documents do not say. I read Volume 2-01 Version 6 and Volume 2-03 Version 6, and neither has a rule on which projects they apply to or a start date. The library I work from lists them as published January 1, 2026, but the documents themselves carry November 28, 2025. That is the authentication date, not a cut-off.

So do not assume a cut-off such as “projects started after January 1, 2026”. The City has not written one in these documents. The tender documents are where the answer should be.

What Version 6 says it changed

Volume 2-01 is titled “Complete Streets Design Standards” (COE-IM-GUIDE-0046). The authentication table is dated November 28, 2025, and every Version 6 entry in the change history is dated November 2025. The change history lists topics only. It gives no widths, offsets or other numbers compared with Version 5. What it says:

  • Added new road functional classes: Expressway, Principal Roadway, Enhanced Local, and Shared Street/Alley.
  • Added content on dimensions and offsets or buffers for shared pathways and bike paths.
  • Removed all references to “main street” and replaced them with “Nodes and Corridors”.
  • Renamed “Shared Use Paths (SUP’s)” to “Shared Pathways (SP’s)”.
  • Removed Section 3.3.1.7, Boardwalks.
  • Removed most of Section 3.5.6.2, “Painted Bike Lanes at Intersections”, to prohibit painted bike lanes at intersections.
  • Revised “Transportation Network” to “Mobility System” throughout.

Volume 2-03 is “Complete Streets Standard Details” (COE-IM-GUIDE-0048), also dated November 28, 2025. Its disclaimer says the drawings are not suitable for a specific project without review and modification, and that deviations or conflicts are to be reconciled with a City representative. Both Version 6 volumes warn that printed or downloaded copies are not controlled and may not be the current version.

The construction specifications

Version 5 was one combined volume, “DCS Volume 2: Complete Streets Design and Construction (Roadways)”, COE-IM-GUIDE-0011. Its change history says Version 5 added the construction specifications and standard drawings chapters, in August 2023.

Version 6 comes as separate volumes. I found the design standards (2-01) and the standard details (2-03). I did not find a Volume 2-02 Version 6 for the construction specifications. The Version 6 volumes themselves say nothing about Version 5 specifications staying in force. The front matter of Volume 2-01 Version 6 still describes the construction specifications as a chapter of the standards.

The only thing I have on this is the City’s own page, as logged on October 21, 2026. It read “Coming Q2/Q3 2026 (Use Version 5 Construction Specifications in the interim)”. I could not confirm that against the City. Its landing page returned an error twice when I tried. Treat it as unconfirmed. I also have nothing newer, and today is October 27, 2026.

The alley amendment

On May 8, 2026 the City of Edmonton, Transportation Assets, issued the “Alley Structural Pavement Design Interim Amendment Notice” (COE-IM-IAN-0002, Version 01). Its parent document is the Complete Streets Design and Construction Standards, COE-IM-GUIDE-0011, version 05, dated August 31, 2023. It gives direction on designing and building residential and commercial alleyway structures, and it names the differences between greenfield development and brownfield renewal and reconstruction as the issue.

It includes red line drawings that replace Standard Drawing 2040 (4.00m Residential Alley) and Standard Drawing 2041 (6.00m Commercial Alley). It says existing specifications will not change unless noted, and that it will be reviewed before the specifications are formally updated. It says standard drawings indicate minimum structures. It also says utility locations, including hydrovac elevations, should be determined and recorded during preliminary design.

The residential alley structure in the notice:

LayerCentreEdge
Unstaged: asphalt 10mm-LT, single lift100 mm100 mm
Unstaged: granular base, Des 3 Class 20 (2 lifts)225 mm300 mm
Alternate granular base: Des 3 Class 20, top lift125 mm125 mm
Alternate granular base: Des 3 Class 63, bottom lift150 mm225 mm
Staged: asphalt 10mm-LT, first lift65 mm65 mm
Staged: asphalt 10mm-LT, final lift35 mm35 mm

Footnote 1 says 10mm-LT placement in a single 100 mm lift is restricted to alley paving. The base goes atop prepared subgrade and non-woven geotextile, or as specified by the engineer of record based on subgrade conditions and City approval.

What the notice does not say: which projects it applies to, when it takes effect beyond its issue date, or whether it goes with the Version 5 or Version 6 drawings. It does not list what changed in Drawings 2040 and 2041 against the Version 5 versions. I did not pull the commercial alley values, so the table above is residential only.

The table of minimum offsets

The Volume 1 Table of Minimum Offsets, edition 2025, gives minimum required offsets across the major reviewing sections. Each tab stands alone. The table says the offsets apply to most cases but may vary for infill or non-standard situations, as determined by the City. Design exceptions go through the Consolidated Design Exception Form. It is a compilation, information only, and needs no engineering authentication. It does not say which version of Volume 2 it follows, and nothing I have says whether it was updated for Version 6.

From the Complete Streets (Volume 2) offsets:

ItemMeasured fromMinimum
Watermain, 400 mm or smallerFace of curb1.5m
Watermain, over 400 mmFace of curb2.0m
Hydrant, any ROW with separate walkFace of curb1.5m
Trees, local (centre of tree)Face of curb1.0m, 1.25m preferred
Trees, arterial (centre of tree)Face of curb2.0m
Storm and sanitary servicesEdge of bus stop pad1.5m
Traffic control cabinetCommercial/industrial access edge of pavement10.0m
Edge of shared-use path, walkway or sidewalkProperty line0.3m

Before you price

  • Look for a version number in the specifications or the tender documents. If one is named, price to that version.
  • If none is named, ask the City in writing before the bid closes. The documents will not answer it for you.
  • On an alley, check whether the amendment is in the bid package, and which drawings 2040 and 2041 you are pricing from.
  • Keep a printed copy’s date in mind. The City says uncontrolled copies may not be current.

Checked against the City of Edmonton’s Complete Streets Volume 2-01 Version 6, Volume 2-03 Version 6, Volume 2 Version 5, the Alley Structural Pavement Design Interim Amendment Notice (COE-IM-IAN-0002), and the Volume 1 Table of Minimum Offsets (2025) on October 27, 2026.