If you price work to the City of Calgary’s standards, two things can change a line on your schedule: the 2025 sewer and waterworks specifications, and a July 2026 bulletin that replaces Sheet 61A. The first took effect on January 1, 2025. The second says its updates are effective immediately. Neither one tells you what it costs, so the work is yours: read the right pages before you price.
The 2025 bulletin lists nothing
The City of Calgary’s Industry Bulletin on the 2025 specifications is dated January 6, 2024. It says the Standard Specifications Sewer Construction and the Standard Specifications Waterworks Construction have been updated. It says the revised specifications are effective as of January 1, 2025.
It is one page. It does not itemize a single change. It points you to the City’s online specification pages and gives two City contacts. The documents do not explain the gap between the bulletin’s date and the effective date.
The itemized changes are in the front matter of each specification. Each has a list of revisions, and the 2025 revisions are marked in bold italics. Neither the bulletin nor those lists name an earlier edition they compare against, so read them as a list of what is marked for 2025 and nothing more.
What the Sewer specification marks
The Standard Specifications Sewer Construction has a front-matter list described as “a list of technical revisions”. Among the 2025 entries:
- Supplier names changed: Inland to Heidelberg, Napco Royal to Westlake, and Next to Next/Groupe Brunet Polymers.
- “Sanitary Sewer” changed to “Wastewater”, and “Storm” changed to “Stormwater”.
- Section 402.01.05: a 3000mm Manhole Riser (Standard Barrels) added, and manufacturers and suppliers updated to AASHTO Certified Suppliers.
- Section 402.01.01: a 1200x1200 Concrete Box Culvert added.
The renamed suppliers and the new terms matter when you read a quote or a schedule line. If a supplier’s name on the quote is not the name in the spec, check the 2025 list before you assume it is a problem.
What the Waterworks specification marks
The 2025 Waterworks specification has its own list, “2025 Waterworks Construction Specification Revisions”, with the same bold-italics convention. It says:
- Section 503.01.00: product list reorganized.
- “PE-RT” added as a water service pipe material, with a new section 503.02.18 for PE-RT service pipe.
- Under 503.01.00 (10): Wirsbo (AquaPEX) removed as an approved product, and CB Supplies (LYNX-PEX) added.
- Cathodic protection requirements consolidated in a newly titled Section 505.00.00, with all references updated.
- Section 503.02.08: a new section for Insert Valves/Line Stops.
Because the product list was reorganized, a section number you remember may not be where you left it.
The Sheet 61A bulletin, July 2026
This is an Industry Bulletin dated July 2026. It updates Section 503.01.00 (15) “Service Line Couplings” and Sheet 61A, “50mm Flushing Assembly Type 'A'”, in the 2025 Waterworks specification. The reason it gives: the update provides new materials better suited for underground construction, to ensure longevity and safety for operators.
Before the amendment, 503.01.00 (15) read “Manufacturers as listed for Main Stops and Service Valves”. The replacement clause splits couplings into two groups:
| Coupling | Manufacturers |
|---|---|
| Inline Couplings | Manufacturers as listed for Main Stops and Service Valves |
| Restrained Couplings | Pack Joint by Mueller, Lead-Pak by Ford, CAMPAK by Cambridge Brass or approved equal |
The bulletin says the current Sheet 61A is removed and replaced. The new sheet removes the “Sharkbite” style coupling and references the new Restrained Coupling approvals in 503.01.00 (15). It also sets a minimum and maximum limit that service pipe may extend above ground. The bulletin text does not give those limits, and the sheet is a scanned drawing whose text does not extract cleanly, so I am not quoting numbers. Open the sheet itself. Its revision block shows revision 8 dated 2026/05/27.
The bulletin says the next version of the Waterworks specification will capture the changes. Until then, the 2025 book and the bulletin have to be read together. The contact is StandardSpecifications@calgary.ca. The printed date is July 2026, and the exact publication date is uncertain, so use the date as printed.
The documents do not say whether Restrained Couplings are required or only permitted beyond the quoted clause. If your service connections include a flushing assembly or a coupling, that is a question for the City contact before you price it.
Checking a supplier quote
Waterworks 503.01.00 is “a list of approved materials”, approved by Standards & Specifications, Utilities Delivery (UD-SS) against standards such as AWWA, CSA, ASTM, UL, FM and NSF and testing of manufacturers' samples. Sewer 402.01.00 holds the equivalent lists. Checking a quote against those section lists is the sensible first step. That is my inference, not something the documents spell out.
The City’s March 2026 Water Utility Product Approvals document does not contain a product list, so it will not help you with a quote. It describes how a manufacturer applies for approval. Some of what it says is still useful to know:
- Applications go by email to StandardSpecifications@calgary.ca, and each product requires a separate submission.
- Outcomes are Approved, Conditionally approved, Not approved and Tabled.
- Conditional approval is limited to pre-approved applications, locations, or a limited time to address a specific market need.
- A Tabled product may be used at the discretion of the designer, project manager or approver, but gets no blanket approval.
- Administrative Review takes approximately three months, Technical Review an additional six to twelve months, and a Trial Installation typically lasts two years.
Waterworks 503.02.01 says written approval of the Engineer is required for all products incorporated in the distribution system, and that only a complete product line will be considered. For sewer, section 402.02.00 says materials not listed may be acceptable case by case, with prior approval from Standards and Specifications, Utilities Delivery.
A manufacturer’s design change to an approved item may result in the City withdrawing an approval. The City may also suspend or rescind an approval if a product fails to perform as specified or lacks local distribution, representation or support, and may publish an Industry Bulletin when it does.
What the documents do not say
They give no cost or schedule effect for any change. They do not say whether any City list applies to other municipalities. They do not say how much of the 2025 revisions affect a given job.
If you are short on time, read the two front-matter lists and the Sheet 61A bulletin before you open the unit price schedule.
Checked against the City of Calgary’s Industry Bulletin on the 2025 specifications, Standard Specifications Sewer Construction 2025, Standard Specifications Waterworks Construction 2025, the July 2026 Sheet 61A Industry Bulletin, and the March 2026 Water Utility Product Approvals on October 27, 2026.