If you are bidding a job on a City of Calgary or City of Edmonton street, traffic control can put permit fees, plan design charges and plan requirements into your price. Some of those have a number in the City’s documents and some do not, so it is worth knowing which is which before you add up the bid.
Both cities publish a temporary traffic control manual, and both cities decide what you submit based on the work. Nobody has time to read every page of both. This is what the documents say, and where they stay quiet.
Calgary: when a plan is required
The City of Calgary issues its Temporary Traffic Control Manual as the 2025 edition. It supplements the national uniform traffic control devices manual and cites Bylaws 20M88 and 26M96 as its authority. It is signed by the Senior Leader ROW Services and the Manager of Traffic Services. The documents do not say what changed from earlier editions, so I will not guess.
Calgary’s flow chart sets the plan requirement from two inputs: road classification and posted speed. Four classifications on the City’s roadway classification map are treated as the arterial 60 km/h or less category: industrial arterial, urban boulevard, neighbourhood boulevard and parkway. The exception is where the speed limit dictates otherwise.
The flow chart also defines a single lane closure as impacting only a single lane of traffic. A multiple lane closure impacts more than one lane. Calgary’s examples are two-way traffic, full road closure and flagging.
The flow chart is a graphic. The text I can read gives the definitions and the outcomes, but not which road class and speed lead to which outcome. I am not going to state that mapping. Look at the chart itself for the road you are working on.
The outcomes are:
- Submit TCP using manual: submit a plan to traffic for approval, referencing the manual, and obtain a street use permit.
- Use traffic manual: obtain a street use permit or have a city-wide annual street use permit. If a transit stop is impacted, notify traffic.
- Site specific TCP, authentication required: submit a site specific authenticated plan to the Traffic Services Division for approval and obtain a street use permit, regardless of the road classification. It must follow Association of Professional Engineers and Geoscientists of Alberta standards.
Calgary: what the application and the site ask for
The manual’s worksite checklist says all work on City-owned right-of-way needs authorization and permits. It lists the Street Use Permit, Hoarding Permit, Excavation Permit and Indemnification Agreement, among others. It also asks whether a temporary no parking permit is needed, and says those need custom time decals showing the start and end times of the work zone.
The Appendix A street use permit application asks for more than the drawing: a copy of the excavation permit, a traffic impact study, a communication plan and a tree protection plan. It also asks for an alternative plan to open the roadway in unexpected circumstances.
Submitted plans must be clearly legible, site-specific, drawn to scale and created in professional software (CAD or equivalent). They must state the set up and removal dates and times. The City may decline unacceptable applications, and the applicant keeps professional responsibility for the work.
Two more items:
- Signal-timing disruptions must be coordinated with Traffic Services at least fifteen business days before the work starts.
- Work within Deerfoot Trail or Stoney Trail right-of-way is provincial jurisdiction and needs approval from Alberta Transportation.
The permit holder or contractor maintains the devices for as long as there is an obstruction to traffic.
Edmonton: the manual and the permit matrix
The City of Edmonton issues its Manual of Temporary Traffic Control as COE-IM-GUIDE-0024, Version 6, with a cover date of January 31, 2023. It grew out of the 2012 Procedures for On-Street Construction Safety Manual, supplements the national manual, and is developed under Traffic Bylaw 5590. The Parks and Roads Services Branch developed it. The documents do not say what changed in Version 6.
Its layout series are:
- Series A: complete and partial road closures, examples A1 to A6.
- Series B: includes flagging layouts, B1 and B2. The section title did not come through in the text I have, so I am not titling it.
- Series C: pedestrian and cyclist accommodations, examples C1 to C7.
On site, the manual says to keep a copy of the OSCAM permit and Traffic Accommodation Plan, and to display the permit publicly. It also requires the site to be restored to a condition equal to or better than before the work started.
The OSCAM Permit Decision Matrix works in three steps: determine the condition, determine the location and duration of the work, then read the decision point that says whether a permit is required. It also says the appropriate level of temporary traffic control is required at all times, whether or not the work needs an OSCAM permit.
The matrix shows a permit as needed in all locations for two conditions: a temporary crossing of a sidewalk or boulevard to reach private land from a public roadway, and excavation of roadways, sidewalks or boulevards.
For other work, the matrix splits peak hours from non-peak hours. Peak hours are 6:00 to 9:00 and 15:30 to 18:30, Monday to Friday, excluding holidays. It defines very short operations as 1 hour or less, short operations as stationary work between 1 and 24 hours, and long operations as stationary work over 24 hours. For residential roads, mobile work is “No” and long-duration work is “Yes”, in the peak rows and the non-peak rows alike. The peak and non-peak rows are hard to read from the text, so I am not stating the arterial or collector answers.
Edmonton: the fee sheet
The OSCAM fee sheet sets the permit at $25.00 per day. Temporary Crossing, Tree Shrub Hoarding, and Commercial Waste Bin, SeaCan and PODS permits have no charge. A daily fee for waste bins, PODs and SeaCans is planned but on hold until further notice.
Plan design and review is priced in units at $100 per unit:
| Category | Design | Review |
|---|---|---|
| A Basic (sidewalk closure, no parking, single lane closure) | No charge | No charge |
| B Intermediate | 2 units | 1 unit |
| C Complex | 2+ units | 2 units |
| D Coordination (cancellation or change request) | No charge | 1 unit |
| E Resubmission | 1 unit | 1 unit |
The printed footer on the fee sheet reads “Last Updated: April 29, 2021”. The sheet’s own text gives no 2025 date. I am not calling this a fee change, and nothing here says fees rose.
For plans on detours, Edmonton requires authenticated Traffic Accommodation Plans on urban roadways with a posted speed of 70 km/h or more. It says certain projects on roads under 70 km/h may also need one, depending on the complexity of the project and its impact on the travelling public. It names no further criteria.
What the documents do not say
None of these documents says which costs belong in your traffic accommodation line. The fee sheet prices permits and plan design and review. The manuals cover devices and plans. Any split of those into one line is a judgment call, and you should make it knowing that.
The documents also give no cost for traffic control devices, flaggers, traffic control persons, or plan preparation by a professional engineer. Calgary’s street use permit fee is not in the documents I have. They give no permit turnaround times, and they do not compare the two cities. These are costs to check before the bid goes in, and they will not come from these pages.
Checked against the City of Calgary Temporary Traffic Control Manual (2025), the Calgary temporary traffic control plan flow chart, the City of Edmonton Manual of Temporary Traffic Control (Version 6), the OSCAM Permit Decision Matrix, the OSCAM fee sheet and the Edmonton authenticated Traffic Accommodation Plan notice on October 27, 2026.