Schwehr Projects · Services · 02 · Estimating

Construction estimating services for heavy civil, earthworks, utility and aggregate contractors.

A complete estimate from your drawing set: quantities, crew and equipment productions, material and subcontractor quotes, indirects and a scope sheet, in a workbook your own estimator can check line by line. Road and earthworks jobs, subdivision servicing and underground utilities. Fixed fee per bid, from Edmonton for contractors across Alberta and BC.

Who this is for

Contractors who bid more work than one estimator can price.

The owner who still estimates

You run the company and the bids. When three tenders close in the same week, one of them gets priced at midnight. This service takes the one that would otherwise be rushed or passed on.

The contractor between estimators

Your estimator left, or you are not yet big enough to carry one. Bids still need to go out. A fixed fee per bid costs less than a salary and nothing in a quiet month.

The estimating department at capacity

Overflow for a larger contractor: a complete estimate in your format, built on your rates and productions, ready for your chief estimator's review and markup.

The excavation contractor stepping up to civil

You have the excavator, the crew and the local reputation, and a developer has asked you to price sanitary, water and road restoration to a municipal specification for the first time. The estimate, the spec reading and the proposal come from someone who has done it before.

The subcontractor pricing to a GC

Earthworks, aggregates, underground and grading subs who need a tight, defensible unit price schedule to hand up to the general contractor before their deadline.

What the estimate includes

Direct costs built up from crews and productions, not from a lump sum.

  • Quantities. My own takeoff from the drawing set, or yours if you have one, with every line traced to its drawing.
  • Crew and equipment build-ups. Each work item priced as a crew (labour, equipment, small tools) at a stated production rate, so the unit cost is labour hours and machine hours, not an opinion.
  • Equipment rates. Your internal ownership and operating rates, or built from fuel, wear and ownership assumptions. BC MoTI Blue Book and HETS rates applied where an owner requires them.
  • Materials. Supplier quotes requested and compared, or budget prices flagged as such until the quote arrives.
  • Subcontractors. Quotes compared and levelled for scope so that the lowest number is also the complete one.
  • Indirects and general conditions. Supervision, site facilities, survey, mobilization and demobilization, bonding and insurance, traffic accommodation, fuel escalation and weather allowances listed and priced separately.
  • Scope sheet. Inclusions, exclusions, assumptions and RFIs written while the quantities are fresh, ready to attach to the submission.
  • Bid form or lump sum. Unit price schedule populated with the unit rates and extended totals where there is one; a priced section summary for a lump-sum proposal where there is not. Markup and contingency stay as inputs for you to set on bid day.
  • Quotes requested on your behalf. RFQs to pipe and fittings suppliers, aggregate pits, paving and concrete subs, hot tap and testing contractors, shoring and traffic control rentals, tracked on one sheet until every plug is a quote.
  • Risk register and contingency. The things that could go wrong, each with a probability and a cost, so the contingency is a number you can defend rather than a round percentage.
  • Cost-driver summary for your bid review. A one-page list of the ten items that make up most of the price, the assumption behind each one and how far it could move, so the review meeting starts with the decisions.
  • Schedule and execution plan. A crew-day schedule in ProjectLibre and a short execution plan that the proposal narrative and the durations are taken from.

What you get

Every unit rate shows the crew, the production and the hours behind it.

The estimate workbook has a tab for quantities, one for crews and equipment rates, one for the build-ups and a summary in bid-form order. Change a production rate or a fuel price in one cell and every affected unit rate updates.

Items priced on an assumption carry a flag and a note, so your bid review meeting starts with a list of the risks rather than a search for them.

Sample build-up · 200 mm sanitary main, 2.5 m deep, shored trenchIllustrative figures
ResourceRoleRate /hHoursCost
Excavator, 20 t classDig, lay, backfill195.006011,700
Skid steerEmbedment and backfill140.00608,400
Foreman and two pipelayersCrew, straight time plus OT180.006010,800
Shoring box and compaction rentalsPer crew hour in use45.00602,700
180 m at 30 m per 10-hour day186.67 /m
Production, hours per day and crew make-up are inputs on the crew tab. The 186.67 is labour and equipment only; pipe, embedment and imported backfill come in from the quotes on their own lines, and indirects and markup are applied on the summary.

Pricing and turnaround

A fixed fee per bid, agreed from the drawing set.

Fixed fee per bid

Quoted within one business day from the drawing count, the number of bid items and the close date. The fee covers takeoff, build-ups, RFQs, quote levelling, scope sheet and a walkthrough call before closing. A first takeoff is usually back within a day or two of the set; the finished estimate follows the supplier quotes and your answers to the assumptions list, typically five to eight working days on a small job.

Hourly for reviews

A second set of eyes on an estimate your team built, a pre-bid budget to decide whether a job is worth pursuing, or sitting in on your bid review are billed hourly.

What I need from you

Drawings, specification, bid form and addenda; your labour and equipment rates if you want them used; a list of subcontractors and suppliers you want quotes from; and the markup approach you prefer.

Terms

Invoice on delivery, net 30. Contractors with a steady bid calendar work under a master agreement with a fee schedule by bid size. First bid for a new client at a reduced fee.

Questions

What contractors ask before the first job.

Do you use our rates or yours?

Yours, wherever you have them. Labour, equipment and historical unit costs from your past jobs make the estimate yours rather than generic. Where you have none, rates are built from first principles and shown so you can adjust them.

Do you submit the bid for us?

No. The submission goes out under your company name and signature. I prepare the estimate and, if you want it, the tender package; you decide the markup and sign.

How is this different from an offshore takeoff service?

A takeoff is quantities. An estimate is quantities priced with crews and productions that fit Alberta and BC conditions: frost, haul roads, short seasons, union and non-union labour, and owner-specified equipment rates. That judgement comes from having run the numbers on a contractor’s side of the table.

Will you be available on bid day?

Yes. The fee includes a walkthrough of the workbook before closing and being reachable on the day for last-minute addenda or quote changes.

What about the work after the bid is won?

The estimate’s cost codes and productions carry straight into cost tracking and forecasting, so the job is measured against the numbers it was priced on.

Where I work

Remote from Edmonton, across Alberta and British Columbia.

Drawings, specs and workbooks travel well, so most work is done remotely for contractors in Edmonton, Calgary, Red Deer, Grande Prairie, Fort McMurray, Lloydminster and Lethbridge, and across the BC Interior including Kamloops, Kelowna, Prince George and the Peace region. Site visits are arranged when a job calls for one, for example a pre-bid walk-through, a pit survey or a start-up week with the site team.

Schwehr Projects Ltd. is an Alberta corporation. Work in BC is done under the same agreement, with BC MoTI Blue Book and HETS equipment rates applied where the owner requires them.

Next step

A second estimating desk for the weeks when yours is full.

Send the drawing set or a short description of the job and the tender close date. You will have a fixed fee and a delivery date back within one business day. First bid for a new client at a reduced fee.